ANALYSIS OF HOUSING CONSTRUCTION TIME IN THE PURBALINGGA REGENCY AREA BY USING THE LINEAR SCHEDULING METHOD

Authors

  • Taufik Dwi Laksono Construction Manajement, Madyathika Polytechnic Purbalingga, Kedung Menjangan Kecamatan Purbalingga Jawa Tengah, Indonesia
  • Dwi Sri Wiyanti Civil Engineering, Faculty of Engineering, Wijayakusuma University Purwokerto, Jl. Beji Kampus Karangsalam Purwokerto Indonesia

DOI:

https://doi.org/10.29121/ijetmr.v12.i1.2025.1529

Keywords:

Time Analysis, Housing Project, Linear Scheduling Method (LSM)

Abstract

The realization of a construction project is closely connected to its cost and time. Work time planning illustrates the time of every work item from start to finish so that the total project completion time can be known. This study is a further analysis of the effects of using the linear scheduling method on total project time in a housing construction project to give a clear overview of potential differences. This study aimed to find the time needed to complete a housing project in Pubalingga Regency.
Using LSM as a scheduling tool provides convenience in planning, executing, and controlling every work item, making it easier for the stakeholders to monitor the progress.
This study concluded that using the Linear Scheduling Method (LSM), the time needed to complete 16 (sixteen) houses in Payodha Residence is 112 days

Downloads

Download data is not yet available.

References

Aprika. (2023, July 7). The Linear Scheduling Method Explained.

Ervianto, W. I. (2002). Manajemen Proyek Konstruksi. Yogyakarta: Andi.

Faisol (2010). Mata Kuliah Perencanaan, Penjadwalan dan Pengendalian Proyek. Yogyakarta: Universitas Islam Indonesia.

Husen, A. (2009). Manajemen Proyek (Perencanaan Penjadwalan dan Pengendalian Proyek). Yogyakarta: Andi.

Sadana, A. S. (2014). Perencanaan Kawasan Permukiman*. Yogyakarta: Graha Ilmu.

Sugiyono (2021). Metode Penelitian Kualitatif: Untuk Penelitian yang bersifat eksploratif, enterpretif, interaktif dan konstrukstif*. Bandung: Alfabeta.

Sahir, S. H. (2021). Metodologi Penelitian*. Medan: KBM Indonesia.

Tania (2022). Perbandingan Jadwal dan Biaya Proyek dengan Linear Scheduling Method (LSM)*. Skripsi, Universitas Pendidikan Indonesia, Jakarta.

Tavener, A. (2023, November 6). Overcoming Delays On Construction Sites With On-time Deliveries.

Undang-undang Nomor 1 tahun 2011 tentang Perumahan dan Kawasan Permukiman.

Utami, A., & Nugraheni, F. (2023). Analisis Penjadwalan Waktu Pelaksanaan Proyek dengan Linear Scheduling Method (LSM) pada Proyek Pembangunan Perumahan. Proceeding Civil Engineering Research Forum, 3(1).

Verolio, & Pamadi. (2023). Analisa Penjadwalan Metode Linear Scheduling Method atau Line of Balance (LSM/LoB) pada Perumahan Devely Residence Kota Batam. *Civil Engineering and Architecture Journal, 1(1).

Downloads

Published

2024-01-31

How to Cite

Laksono, T. D., & Wiyanti, D. S. (2024). ANALYSIS OF HOUSING CONSTRUCTION TIME IN THE PURBALINGGA REGENCY AREA BY USING THE LINEAR SCHEDULING METHOD. International Journal of Engineering Technologies and Management Research, 12(1), 28–37. https://doi.org/10.29121/ijetmr.v12.i1.2025.1529

Most read articles by the same author(s)