ANALYSIS OF HOUSING CONSTRUCTION TIME IN THE PURBALINGGA REGENCY AREA BY USING THE LINEAR SCHEDULING METHOD
DOI:
https://doi.org/10.29121/ijetmr.v12.i1.2025.1529Keywords:
Time Analysis, Housing Project, Linear Scheduling Method (LSM)Abstract
The realization of a construction project is closely connected to its cost and time. Work time planning illustrates the time of every work item from start to finish so that the total project completion time can be known. This study is a further analysis of the effects of using the linear scheduling method on total project time in a housing construction project to give a clear overview of potential differences. This study aimed to find the time needed to complete a housing project in Pubalingga Regency.
Using LSM as a scheduling tool provides convenience in planning, executing, and controlling every work item, making it easier for the stakeholders to monitor the progress.
This study concluded that using the Linear Scheduling Method (LSM), the time needed to complete 16 (sixteen) houses in Payodha Residence is 112 days
Downloads
References
Aprika. (2023, July 7). The Linear Scheduling Method Explained.
Ervianto, W. I. (2002). Manajemen Proyek Konstruksi. Yogyakarta: Andi.
Faisol (2010). Mata Kuliah Perencanaan, Penjadwalan dan Pengendalian Proyek. Yogyakarta: Universitas Islam Indonesia.
Husen, A. (2009). Manajemen Proyek (Perencanaan Penjadwalan dan Pengendalian Proyek). Yogyakarta: Andi.
Sadana, A. S. (2014). Perencanaan Kawasan Permukiman*. Yogyakarta: Graha Ilmu.
Sugiyono (2021). Metode Penelitian Kualitatif: Untuk Penelitian yang bersifat eksploratif, enterpretif, interaktif dan konstrukstif*. Bandung: Alfabeta.
Sahir, S. H. (2021). Metodologi Penelitian*. Medan: KBM Indonesia.
Tania (2022). Perbandingan Jadwal dan Biaya Proyek dengan Linear Scheduling Method (LSM)*. Skripsi, Universitas Pendidikan Indonesia, Jakarta.
Tavener, A. (2023, November 6). Overcoming Delays On Construction Sites With On-time Deliveries.
Undang-undang Nomor 1 tahun 2011 tentang Perumahan dan Kawasan Permukiman.
Utami, A., & Nugraheni, F. (2023). Analisis Penjadwalan Waktu Pelaksanaan Proyek dengan Linear Scheduling Method (LSM) pada Proyek Pembangunan Perumahan. Proceeding Civil Engineering Research Forum, 3(1).
Verolio, & Pamadi. (2023). Analisa Penjadwalan Metode Linear Scheduling Method atau Line of Balance (LSM/LoB) pada Perumahan Devely Residence Kota Batam. *Civil Engineering and Architecture Journal, 1(1).
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Taufik Dwi Laksono, Dwi Sri Wiyanti

This work is licensed under a Creative Commons Attribution 4.0 International License.
License and Copyright Agreement
In submitting the manuscript to the journal, the authors certify that:
- They are authorized by their co-authors to enter into these arrangements.
- The work described has not been formally published before, except in the form of an abstract or as part of a published lecture, review, thesis, or overlay journal.
- That it is not under consideration for publication elsewhere.
- That its release has been approved by all the author(s) and by the responsible authorities – tacitly or explicitly – of the institutes where the work has been carried out.
- They secure the right to reproduce any material that has already been published or copyrighted elsewhere.
- They agree to the following license and copyright agreement.
Copyright
Authors who publish with International Journal of Engineering Technologies and Management Research agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License (CC BY-SA 4.0) that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
- Authors can enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or edit it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) before and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
For More info, please visit CopyRight Section