THE EFFECT OF BRICKLAYER’S WORK METHOD ON TILE INSTALLATION WORKING TIME

Authors

  • Dwi Sri Wiyanti Civil Engineering, Faculty of Engineering, Wijayakusuma Univesity Purwokerto, Jl. Beji Karangsalam 53152, Indonesia
  • Taufik Dwi Laksono Civil Engineering, Faculty of Engineering, Wijayakusuma Univesity Purwokerto, Jl. Beji Karangsalam 53152, Indonesia
  • Atiyah Barkah Civil Engineering, Faculty of Engineering, Wijayakusuma Univesity Purwokerto, Jl. Beji Karangsalam 53152, Indonesia

DOI:

https://doi.org/10.29121/ijetmr.v6.i5.2019.378

Keywords:

Work Method, Bricklayers, Activity Time, Tile Installation

Abstract

The implementation of a construction project consists of several works that carried out by labourer or craftsman in accordance to their specifications of expertise. To achieve both time and quality target of work output, each craftsman use different work method that consists of a series of activities. From a series of activities that carried out by each craftsman, the time needed to complete a work can be calculated. This study observed the activities of bricklayers in tile installation. The method that used in the study of bricklayers in tile installation is a literature study. On the other hand, an on-site study is performed by recording a number of bricklayers in tile installation. The recordings of each bricklayer were studied so that a series of activities and the activity time of tile installation can be obtained. From the observations of 35 bricklayers regarding work method and activity time of the tile installation, 4 (four) work methods were identified. Of all the samples that have been studied, the fastest is the bricklayer number 9 (nine) whose activity time was 7.69 minutes by using the work method number 2 (two).

Downloads

Download data is not yet available.

References

Asmal, Sapta, 2004, Penerapan Telaah Metode Kerja dan Ergonomis Untuk Meningkatkan Produktifitas Kerja Masyarakat Pengrajin Batu Bata, , Lembaga Penelitian UNHAS

Dipohusodo, Istimawan, 1996, Manajemen Proyek dan Konstruksi, Kanisius, Yogyakarta

Dwi Laksono, Taufik, 2001, Metode Kerja dan Produktivitas Tukang Plester Pada Pekerjaan Pemasangan keramik, Tesis Program Studi Magister Teknik Sipil, Universitas Islam Indonesia, Yogyakarta

Ervianto, Wulfram I., 2004, Teori Aplikasi Manajemen Proyek Konstruksi, Andi Offset, Yogyakarta

Ervianto, Wulfram I., 2005, Manajemen Proyek Konstruksi, Edisi Revisi, Andi offset, Yogyakarta

Harijanto, Setiawan, 2006, Efektivitas waktu kerja kelompok tukang, Jurnal Teknik Sipil Volume 7 No 1

Pamuji, 2008, Pengukuran produktivitas pekerja sebagai dasar perhitungan upah kerja pada anggaran biaya, Tugas Akhir Program Studi Teknik Sipil, Universitas Sumatera Utara

Purnomo, Sukirno, 1999, Pengantar Manajemen Proyek, Diktat Kuliah Magister Teknik Sipil UII, Yogyakarta

Silalahi, Bennet, 1994, Perencanaan Pembinaan Tenaga Kerja, PT. Pustka Binwan Pressindo, Jakarta

Soeharto Iman, 1999, Manajemen Proyek dari Konseptual Sampai Operasional, Erlangga, Jakarta

Sritomo Wignjosoebroto, 1995, Ergonomi, Studi Gerak dan Waktu, Edisi Pertama, Guna Widya, Jakarta

Sugiyono, 2011, Metode Penelitian Kuantitatif Kualitatif dan R & D, Alfabeta, Bandung

Sugiyono, 2011, Statistika untuk Penelitian, Alfabeta, Bandung

Suparyono, 2010, Metode Pelaksanaan Bangunan, Pro Estimasi Indonesia. Jakarta

Tamrin, A.G., 2008, Teknik Konstruksi Bangunan Gedung Jilid I, Direktorat Pembinaan Sekolah Menengah Kejuruan, Jakarta

Wuryanti, Wahyu, 2010, Standarisasi pedoman pengukuran Produktivitas Tenaga Kerja untuk Pekerjaan Konstruksi Bangunan Gedung, Prosiding PPI Standarisasi, Banjarmasin

Downloads

Published

2019-05-31

How to Cite

Wiyanti, D. S., Laksono, T. D., & Barkah, A. (2019). THE EFFECT OF BRICKLAYER’S WORK METHOD ON TILE INSTALLATION WORKING TIME . International Journal of Engineering Technologies and Management Research, 6(5), 117–126. https://doi.org/10.29121/ijetmr.v6.i5.2019.378

Most read articles by the same author(s)