PRODUCTIVITY OF CONSTRUCTION PROJECT FROM CONTRACTOR POINT OF VIEW

Authors

  • Taufik Dwi Laksono Civil Engineering, Faculty of Engineering, Wijayakusuma University Purwokerto, Jl.Beji Karangsalam, Purwokerto, 53152, Indonesia
  • Dwi Sri Wiyanti Civil Engineering, Faculty of Engineering, Wijayakusuma University Purwokerto, Jl.Beji Karangsalam, Purwokerto, 53152, Indonesia
  • dan Pingit Broto Atmadi Civil Engineering, Faculty of Engineering, Wijayakusuma University Purwokerto, Jl.Beji Karangsalam, Purwokerto, 53152, Indonesia

DOI:

https://doi.org/10.29121/ijetmr.v5.i12.2018.334

Keywords:

Contractor, Productivity, Completion Time, Construction Project

Abstract

Construction project is a continuous activity that link to one another. If there is a delay in one activity it can make delay to the other activity. One of the factors that affect the project completion time is the productivity of each activity. Research of Contractor point of view on the productivity of construction project is expected to give more actual description of Contractor point of view on work productivity and identifying factors that strongly affect productivity so that it can be used as guidance to take steps to improve productivity in construction project. The method that this research use is questionnaire distribution. This method is chosen because it makes easier for researcher to collect data, saving time, and shorten research time. The research result shows that according to contractor, productivity needs to be increase so that construction project quality also improve. According to contractor poit of view, technology can be used as a solution to increase productivity in construction project.

Downloads

Download data is not yet available.

References

Ambar, T. S., Rosidah. Manajemen Sumber Daya Manusia. Graha Ilmu. Yogyakarta. 2009

Bogdan, R., Talyor, J. Introduction to qualitative research methods : a phenomenological approach to the social science. New York: Willey-interscience publication. 1992

Creswell,J. Research design : qualitative and quantitative approaches. Singap ore:Sage production. 2014

Danang, S. Teori, Kuesioner, dan Analisis Data Sumber Daya Manusia (Praktik Penelitian), Yogyakarta. CAPS

Dwi, T., Sri Murni, D., Sugeng, P.B. Faktor-faktor yang Mempengaruhi Produktivitas Pekerja Pada Pekerjaan Atap Baja Ringan di Perumahan Green Hills Malang. Jurnal Rekayasa Sipil, Vol 6, No.1, 2012

Hamdan, D., Kadar, N. Manajemen Proyek. Pustaka Setia. Bandung, 2014

Idzuraida, I. Keterlambatan Proyek Konstruksi Gedung, Faktor Penyebab dan Tindakan Pencegahannya, Jurnal Momentum, Vol.14 (1), Feb, 2013.

Ilyas, Yaslis. Kinerja Teori Penilaian dan Penelitian. Fekom UI, Jakarta. 1999

Issac, A., O., Godwin, I., I. Influence of Labour-Related Factors on Construction Labour Productivity in The South-South Geo-Political Zone of Nigeria. Journal of Construction in Developing Countries, 19(1), pp 93-109, 2014

Jan, T, Pingkan A.K. P, Walangitan, D.R.O. Analisis Tenaga Kerja Terhadap Produktivitas Pada Proyek Konstruksi (Studi Kasus: Rehabilitasi dan perluasan Rumah Dinas Rektor Unsrat), Tekno, Vol. 14, No. 65. April, 2016

Mahamid, I. Contractors Perspective Toward Factors Affecting Labor Productivity in Building Construction. Engineering, Construction and Architectural Management, Vol 20, Issue 5, pp 446- 460, 2013 DOI: https://doi.org/10.1108/ECAM-08-2011-0074

Mohammed, A.H., Montaser A. H., Ghaleb, J.S. Factors Affecting Construction Labour Productivity: A Case Reseach of Jordan. International Journal of Construction Management, Vol. 16, Issue 2, pp 138-149, 2016 DOI: https://doi.org/10.1080/15623599.2016.1142266

Moselhi, O., Khan, Z. Analysis of Labour Productivity of Formwork Operations in Building Construction. Construction Innovation, 2010. 10(3), 286-303 DOI: https://doi.org/10.1108/14714171011060088

Muchdarsyah, S. Produktivitas, Apa dan bagaimana. Bumi Aksara. Jakarta. 1997 Nasution, Leni Masnidar. Statistik Deskriptif. Jurnal Hikmah, 2017. 14 (1), 49-55

Saryono. Metode Penelitian Kualitatif, Alfabeta. Bandung. 2010

Sedarmayanti. Tata kerja dan Produktivitas kerja. Tinjauan dari aspek ergonomi atau kaitan antara manusia dengan lingkungan kerjanya. Mandar Maju. 2011.

Sekaran, U., Bougie, R. Research methods for business. New York: John Wiley & Sons. 2010

Selviana. Pentingnya K3(Keselamatan dan Kesehatan Kerja) dalam Meningkatkan Produktivitas kerja. Buletin KPIN, Vol 3, No. 10, Oktober 2017

Soepardi, H., Bambang, P.A., Arief, N. W. Pengaruh Produktivitas Kerja Terhadap Keterlambatan Pelaksanaan Proyek Konstruksi Bangunan. Prosiding Temu Ilmiah IPLBI, 2017, C043-C052

Sunyoto, D. Teori, Kuesioner, dan Analisis Data Sumber Daya Manusia (Praktik Penelitian), Yogyakarta. CAPS

Supardi. Aplikasi Statistika dalam Penelitian, Change Publication, Jakarta.2013 The Constructor.org. Delays in Construction Projects, Its Types, Effects and Management

Trijono, R. Metode Penelitian Kauntitatif. Papas Sinar Sinanti, Jakarta. 2015

Undang-undang RI No. 28 Tahun 2002 tentang Bangunan Gedung

ibisono, D. PanduanPenyusunan Skripsi, Tesis dan Disertasi. Andi. Yogyakarta. 2013 www.id.m.wikipedia.org. Kontraktor

Yunita, A.M., Theodorus, W., Marisya, L. A. Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Gedung di Kota Kupang. Jurnal Teknik Sipil, Vol 11, No.2, September 2013

Downloads

Published

2018-12-31

How to Cite

Laksono, T. D., Wiyanti, D. S., & Atmadi, P. B. (2018). PRODUCTIVITY OF CONSTRUCTION PROJECT FROM CONTRACTOR POINT OF VIEW . International Journal of Engineering Technologies and Management Research, 5(12), 123–133. https://doi.org/10.29121/ijetmr.v5.i12.2018.334