1. INTRODUTION Project Management is the application of information, capacities and Techniques to stretch outs to encounter task prerequisites. An essential capacity to achieve  somewhat efficiently for relations. It is very well be characterized as the cycle and movement of preparation, positioning, rousing and controlling assets. Strategies and conventions to accomplish  clear objectives. The task is relied upon to get finished inside the predefined time cut-off and spending plan. There are various programming's accessible in t for project the board. MS task and Primavera are generally utilized for arranging and booking.  Arranging of gigantic ventures requires colossal measure of administrative work, which is decreased with the assistance of P6 and MS project programming. Every product has got its own benefits and negative marks. These apparatuses help us for streamlining the development technique to forestall time and cost to finish the task in arranging span and inside the financial plan. It is planned in such a manner to assist with extending supervisors in making an undertaking plan, allocating assets to task things, keeping tabs on their development, refreshing of venture, allocating by  spending plan, and separating responsibilities. According to T. Subramani (2015)[T. Subramani et al.(2014)] Primavera P6 is a software is not only used by project planners but also involved in project, i.e. managers, engineers, schedulers. Primavera software focusing on the advantages and comparison of  construction estimate methods application in usefulness project. P6 allows users to generate project templets, which can used for future project also. Primavera can also be used to group and view multiple project  at the same time. The resource plays important role in any construction project. It performance of any construction project directly depends upon resource management. The resource optimization and levelling using primavera P6 software about 5.65% resource reduction is observed [ Reddy (2015)]. When  compares MSP & primavera, open workbench for resource levelling in two real time project and the result shows primavera gives most the critically unlimited number of criteria as priority rules. The process and activity of planning, organizing exciting and controlling resources, procedures, to achieve complete goals in scientific or daily problems that help to overcome the problems . It helps for the optimum and effective organization of activities to complete the project in planned duration and within the market.[Castor (2008)] The time performance of the conventional method of
construction for high- rise residential and commercial projects method by
originate level measures of industry norms for overall construction period
using scheduling simulation modelling. The positive changes include creating a
healthy working environment among those involved directly in the construction
industry. Improved Customer satisfaction whenever you get a project done on
time and under budget. It helps easily plan and manage project activities,
optimizes management of all resources and gives clear visibility of project
allows quick and easy forecasting of WBS’s, activities or projects. [Ragavi and Uma (2016), Subramani (2018)].The improper resource
management results in huge amount wastage, also causes increase in time
duration. Using Primavera software, we can organize project properly and
recognize potential problems. Primavera software is used for making project
management easier, especially in difficulties [Umesh (2015)]. Â
Projects are regularly exploited as a method of directly or indirectly achieving points within an organization’s strategic plan. Projects are typically authorized as results of one or more of the subsequent strategic considerations. Planning involves deciding in prior to what’s  to be done, how and in what order it is to be done in order to achieve the objectives. Planning aims at deciding upon the long run course of action. In brief, Planning and scheduling involves a) Collecting and synthesizing information. b) Developing alternative courses of action within specified constraints. c)Comparing alternatives in terms of objectives feasibility and consequences. d) Selecting and scheduling the optimum course of action. e) Establishing policies, procedures, methods, schedules, programs, systems, standards and budgets for accomplishing project objectives. 1.1. Planning AND
Management Project management is that the application of knowledge, skills, tools, and techniques to project activities to satisfy the project requirements. Project management is proficient through the acceptable application and integration of the 47 logically grouped project management processes, which are categorized into five Process Groups. a) Initiating b) Planning c) Executing d) Monitoring, Controlling and e) Closing. In project planning sequencing of the work will work more as compare to unplanned project. The following are the step by step procedure for project planning. a) Make a detailed list of activities b) Prepare a network diagram c) Identify the critical path d) Allocate the resources or juggle the schedule The mail objective of the project mission is unique and it is based on different sits and locations. In this project, it has been comparison between two software’s   for calculation the project completion days. Entire project schedules with different break down structures   is compared with other software and procedures adopted. It is difficult to monitor the project from corporate which makes a challenge in coordination with the site management and the management team. Project execution involves working in dangerous condition (heights, depths etc) which may have the chances of more accidents as compared to other industries. Project functioning under higher peril and uncertainty when associated with construction practices as the lack of time flexibility is due to completion of the project. As the delays during the execution can impacts the subsequent activities work schedule and which may results in paying high penalties from the vendors or from the client to the vendors.  Project not only depends on the timelines but also the quality of the work is also most important in any project and different commercial, residential, infrastructure projects has standards which is to be followed and maintained throughout the project. In case of any defects entire exaggerated work may get rejected or the partial work. Either has impact on the time cost, timeline of the projects and which may demotivate the project team. If the quality is not maintained properly and regular interval inspection is not done during the execution which will be further impact in the operations of any projects and handing over or closeout of the project. 2. Research Methodology A project life cycle could be a collection of generally sequential and sometimes overlapping project phases whose name and number are determined by the management and control needs of the organization or organizations involved within the project, the nature of the project itself, and its area of application. The life cycle provides the essential framework for managing the project, regardless of   the   specific   work involved.  Irrespective of how large or small, simple or complex, all   projects can   be   mapped   to the following life cycle structure. a) Starting the project b) Organizing and preparing c) Carrying out the project work, and d) Documenting and handover of project & closeout. This generic life cycle structure is commonly observed when communicating with upper management or other entities less at home with the main points of the project [Dubey (2015)]. This high -level view can provide a common frame   of   reference for comparing projects—even if they are dissimilar in nature.
Function of Â
project management are different as compared to different projects but as  summarized five basic functions of project
management is followed in all project execution for smoothly completion of project.Â
a) Planning b) Organizing c) Staffing and provisioning resources d) Directing
or leading e) Controlling. ThereÂ
must be anÂ
categorical operational planÂ
to guide the entireÂ
project. The plan must   includeÂ
and link the three
components of the project: scope, budget and schedule. Too often, planning is
focused only on schedule without regard to the important components of budget
and scope. This process starts with WBS. Planning, scheduling and controlling
begin at the inception of the project and continue till the life of the
project until completion. In this study a hotel project is
considered and  planning and scheduling
using software’s MSP and Primavera is used and comparative study is conducted. 2.1. Microsoft Project (msp) Project management wares, software product, introduced & developed by Microsoft. It assist a project manager in developing a planning, assigning resources to tasks, tracking progress, managing the budget, and analysing workloads. Project creates budgets assignment work and resource rates. Resources are assigned to tasks and work is estimated. Program calculates the cost, suitable to the work times the rates. Resource defines (people, equipment and materials) may be shared between projects employing a shared resource pool. Each resource can have its own calendar, which defines days and shifts a resource is available. Resource rates are used to calculate resource assignment costs which are revolved up and summarized at the resource level. Each resource can be a signed to multiple tasks in multiple plans and every task can be assigned multiple resources. Schedules task work based on the resource availability as defined in the resource calendars. All resources may be defined in label without limit. MSP unsuitable for solving problems of available materials.  Calendars option are less as compare to primavera software and due to which outcomes of the schedules may vary and changes entire project dates. 2.2. Primavera P6 Primavera was launched in 1983 by Primavera Systems which was acquired by Oracle Corporation in 2008. Primavera is an enterprise project portfolio management software. It includes project management, scheduling, risk analysis, opportunity management, resource management, control capabilities, and integrates with other enterprise software such as Oracle and SAP’s ERP systems[ Subramani et al. (2017), Veena and Vijay (2016)]. This software is designed for project, program, and portfolio management. It is a powerful, easy to use solution for planning, managing and executing projects. Primavera incorporates a huge performance and easily can’t  be beat. Installing local software on PC cut’s out the lag of web-based products and screen refreshes. It makes P6 professional tool for scheduling projects. Calenderers options are more in the software which is very precise in outcome of schedules. 2.3. Comparison
between MSP and Primavera software Each software’s has its own uniqueness in calculating
the projects timelines and it has different baselines, calendar’s in resources,
costing, etc. and some several users also works on a single project with
specific features. In MSP project can be
can be stored in the disk for future reference and also stored in the servers. It
allows creation of different activities under different WBS and with different
Id’s which allows creating of proper costing, expenses etc. Primavera P6 is one
of the planning software which provides the details entirely about the about
the project at micro level as it has auto levelling of resources   schedules dates are calculated. As compared to MSP, Primavera has more baselines creations based on project requirement. It doesn’t allow the multiple workers using of single project and has restriction because of safety of project document as multiple user may mislead the project scheduling, costing etc. In this software activity cannot be created when and where it is required as it has to follow the WBS and create activities. As it supports exclusive ID article and the activity ID is reliant on the location of the activity. Activity can be controlled as individual activities and which can be moved from their positions to where it to display. It is best suited in developing countries as software is costlier as compare to MSP.
3. Results AND Discussion A hotel
building with B2 +G+11 storey building was considered for the study. Planning
and scheduling is done with MSP and PrimaveraÂ
and detail analysisÂ
is conducted. Results of the analysis says 120 days was extra needed to
complete the project in Msp as compared to P6. 3.1. Data Analysis using MSP By Msp
entire scheduling with baseline calendars is done with different activities
precisely to know the number of days
required to complete the project. Each
WBS has different days and total project days has been calculated with the
maximum/critical activity days of the  activates
considered. As the hotel project required the mock-ups for the guestrooms and
approval from the management and different consultants for the civil
structural, MEP, Interiors, landscape and hardscape of the project. As these required précises calculation so
that project is completed without hindrances. After calculating the project
days it has been compared with Primavera P6 for more information about the scheduling, Resources, costing. MSP
calculation found more project days as compared to P6. By optimization and
analysis of the p6 software days and WBS dates are calculated and reduced by
5%,6% and finally by 8% project timelines of the both software were matched.
3.2. Data Analysis using Primavera In Primavera p6 also calendar’s to be set has
different calendars setting by which different WBS can be set and analysis of
design in the way such that Entire WBS to be created first, below each WBS
activity to be created.  As the
predecessors are given optimized date is calculated by the use of the calendar
opted. Project final dates are reflected. Once the final dates of the activity schedule,
resources schedule is done, it is analysed along with comparison with MSp for
the optimization results. As Primavera
is designed in better way it give précises dates, in this project analysis I
have got 4months early closer of the project as compared to Msp.Changes main
occurred due to the different calendars option in the P6 which will help to
know the exact dates which is required in the project.
|