QUANTIFYING THE UNKNOWN: A MONTE CARLO APPROACH TO COST CONTINGENCY AND RISK ASSESSMENT Dr. Neeraj Chauhan 1 1 Maharshi
Dayanand University, Rohtak, Haryana, India
1. INTRODUCTION When it comes to resource allocation for running a project, one of the hardest challenges would be the need to obtain reliable cost estimates while noting that uncertainties always surround any project. Traditionally calculated CPMs are often not very analytical on risk accounting and often many may confine themselves to approximations that make them overlook many areas of prospecting extra costs, hence a probable reason for underestimation of the costs aspect and probably likelihood of going over budget. Since the efforts increase in complexity and involve various aspects, there is a need to adopt complex methods, which can provide more accurate estimations Aven (2016). Known as a powerful probabilistic model, Monte Carlo simulation proves to be an effective tool for overcoming these challenges. By the use of various scenarios that are generated by…samples of input variables, it is a good basis for driving the probability of uncertainty and quantifying the effects of risk factors to the expenses on the project. As compared to deterministic models that require single estimates, this particular method provides a range of probability distribution on the forecasted cost that is linked to a project Baillie (2015). This paper looks into the use of Monte Carlo simulation with the purpose of assessing cost contingencies and risks within the field of project management. It tries to advance the way decision-making progress in project organisation and oversight by focusing on the consequence of variability in cost evaluation and identifying potential risky aspects. The study also evaluates the benefits of using this approach, which include; better definition of cost estimates, better identification of risk areas, and better decision making to mitigate financial risks Barlow and Proschan (2017). This paper aims to discuss the specifics of applying Monte Carlo simulations and the experience of using it to improve the results of the project with the help of case and exemplar analysis. 1.1. Background of Cost Estimation in Project Management The biggest challenge of cost estimation is to foresee the exact cost that is required to complete a given project and hereby make an efficient plan. This mainly involves estimating costs of all requirements essential for a project including manpower, materials, tools and overheads that are expected to be incurred in executing the project in line with its scope, time and quality parameters. Every project requires cost estimations in order to maintain efficient organizational and financial control; it is the essence of successfully managing and utilizing cost effective and appropriate resources and addressing existing issues in the most suitable way. Earlier, the cost estimation in project management was carried out through basically qualitative methods such as expert opinions, historical data, and other conventional methods like analogous cost estimating, parametric cost estimating methods, and last but not the least, the opinion of experienced professionals. While these techniques provide the preliminary solution of the problem, they often lack the reliability and efficiency in terms of accuracy, especially in such tasks that involve high variability or complexity. Hence there are number of obstacles that still persist, in relation to financial issues including budget overruns, timescale delays, and discrepancies Beasley and Tootell (2018). Recently, due to the need to utilize better and accurate cost estimation models, sophisticated methods including Monte Carlo simulation have been adopted. These methodologies make it possible for the project managers to also take the variation and volatility issues into consideration in aspects to do with cost estimates and finally provide a more accurate and detailed outlook on the conceivable financial performances. The shift from the deterministic models to probabilistic ones such as Monte Carlo analysis represents a shift in paradigms in how expenses are estimated and managed in projects increasing basically the probability of success of a project. Thus, cost estimation becomes a critical factor as the projects develop into rather complex activities that affect many stakers, resources, and circumstances. Although it works hand in hand with cost estimating in ensuring that enough funds are raised to support the project, the process plays the role of an assessment tool for project performance, financial control, and risk minimization for the whole period of the project Beck (2019). Cost control is an important factor when it comes to managing any project so that there is leadership in costs. It enables the project managers to devise realistic budgets, allocate resources and ensure that costs incurred do not go beyond the set financial goal. Belton and Stewart (2018) Budget estimation provides the defined vision on cost of the project so that financial loss of investment or over expenditure is minimized. This also helps in identification of risks such as fluctuation in the price of materials or availability of employees, and allows for setting aside some amount of funds to counter these uncertainties. Furthermore, adequate cost predictions are crucial for building positive attitudes of stakeholders because they offer accurate assumptions on the monetary requirements and help in making effective decisions during the course of the initiative. In conclusion, cost control is an important principle in determining resource productivity, improving the completion of the project, to make sure that it is accomplished with the amount of money allocated for it successfully Blanchard and Fabrycky (2017). It will be nevertheless very challenging to make right estimations of the expenses incurred during projects since it is an exercise that involves a broad range of variables that causes variability. This provides a challenge to predicting future costs for the business since cost might change in accordance to fluctuations in cost of materials, cost of labour, and other external factors which may include economic changes, shift of policies, or natural disasters. It makes cost estimations an issue especially if such an undertaking is lengthy or complex in nature Brown and Hwang, (2017). Another challenge that arises from this is the lack of reliable data and this means that the company often finds itself estimating costs based on assumptions. Lack of historic data or sometimes outdated data can distort the projection results, vice depending on the so-called expert forecast to a certain extent may be subjective and contain biases or errors. Further, factors such as change in project requirements or project timings or the change in the design during the project implementation bring about situations whereby the cost of a project rises and exceeds the estimated cost. This hinders or complicates mission by challenging how goals are accomplished in the complexity of modern projects. Modern activities often combine a large number of parties, various specialty areas, and interconnected activities – which makes it challenging to determine all potential costs and their interdependence. The interactions between the components of the system are complex and require that even a slight change of a segment greatly affects some amounts of financial cost; thus, it hampers direct forecasting of the costs of various segments. Finally, there is always a need to make estimates quickly and actually, many decisions are made based on limited information and poor calculations merely. This may cause some loss of precision in the assessment and it may turn out to be quite cumbersome in the long run if the project goes beyond the said financial plan. To overcome these challenges, there must be an organized approach in cost estimation that embraces risk analysis methods and sophistication instruments in modelling to increase the reliability of the cost estimates. 2. LITERATURE REVIEW 2.1. Understanding Uncertainty in Project Management Uncertainty in project management refers to the variability of a number of factors invasive the outcomes of the project, in particular, temporal and economical outcomes. These elements are often unpredictable because they touch on many aspects of a project such as the availability of human resource, material costs, weather conditions or changes in laws regulating project development Clarke and Mattern (2016). It can result from changes inside the project like changes in the background of the project work, or changes within the availability of resources, changes in the economic climate, political instabilities among others. Risk management is central to the success of any project for it helps the project managers to see what may go wrong as well as plan how to proceed, in case of such a scenario this ensures that the right decisions are made and this makes it possible for the project to be accomplished in the right manner within the laid down scope, time frame and financial resources in line with proficient resource allocation. In order to address this issue, it is necessary for the project leaders to introduce more effective tools of risk management in assessing different forms of outcomes as well as the impact that the changes may have on the cost, time, and performance of projects Coyle (2016). Widely employed, conventional cost estimating techniques have had their roots in the project management for a long time and are handy but constrained in conditions of risk. Since projects are becoming more complex and are able to have many factors that are hard to measure and quantify, existing techniques for risk analysis often provide limited insight into all potential factors that can affect cost estimations. The basic deterministic models that build on the point estimates do not take into consideration the normal variation of the project costs such as labour costs, material cost, and delays in time line among others Der Kiureghian and Ditlevsen (2017). This may lead to unrealistic budgeting, and turn projects vulnerable to cost overruns and contingencies, Drucker (2017) There is therefore need for advanced tool that can assess such risks, to help the project managers make better decisions, prepare for the worse and better manage potential threats. This greatly helps when compared to a single projection, thereby bringing in more precise methods such as Monte Carlo simulation. This approach provides a clearer picture about the potential risks and improves the formulation of measures to mitigate the risks in question. Glickman (2016) 2.2. Introduction to Monte Carlo Simulation The Monte Carlo simulation is a strong quantitative method used to represent uncertainty of complex systems. This method has been given this name due to the Monte Carlo casino situated in Monaco since this one involves the use of random sampling to simulate various outcomes Hillson and Simon (2017). Monte Carlo simulation in the context of project cost estimation involves probability distribution for a number of factors of a project such as labour and materials cost and time among others in order to generate a number of possible outcome or result. As a result of performing many or even millions of iterations, Monte Carlo obtains a probability distribution of the possible expenses of the project, which helps to prepare the project manager for various results. The Monte Carlo simulation is particularly valuable in initiatives that are associated with considerable risk or complexity because it supplies a superior understanding of the range of costs relative to the method of estimating Hoffmann (2018). The Monte Carlo simulation is crucial in the cost estimation since it means a more accurate and closer approximation to the real cost in case of accommodation of some uncertainty. It is almost opposite to the other approaches where only the best estimate is used primarily, Monte Carlo simulation calculates a range of possible cost outcomes in light of the randomness inherent to the project parameters. In this regard, this method helps the project managers to understand the possibility of the diverse costs situations arising in the projects and in turn come up with more accurate cost risks&Solutions . For instance, while a fixed amount is normally used when estimating costs of material, the simulation is likely to use the probability distribution since costs are bound to fluctuate over the period of a project. It leads to enhanced comprehensiveness of financial risks involved in the project along with better management of resources and budgets. Kunsch (2017) Thus the Monte Carlo simulation presents an opportunity to identify the key cost drivers, which provides for better understanding of the most significant cost parameters. This data is useful to guide the attention of the project managers to focus on areas, which are particularly vulnerable to mishaps. Furthermore, it is also applicable and flexible and can be applied to construction projects, information technology projects and engineering projects management and thus is extremely useful in the current project management practice. By incorporating Monte Carlo simulation in cost estimation, it is possible for the project managers to enhance the ability of estimating costs, minimize risks associated with costs, and improve the competency of predicting costs in projects Laituri (2017). Project risk management is the most common area where the Monte Carlo simulation is used as an approach to measure risk. It is important for determination and to moderate risks arising from potential expenses and time that could be incurred within projects. That is the primary strength of Monte Carlo simulation to depict and quantify risks by imitating all the possibility of outcomes originating from random elements. In the range of Project management risk analytical work means the calculation of probability and potential effects of various risk factors that affect the choice of the budget, time, and efficiency of a project. The Monte Carlo simulation make this process easier here because through setting up numerous rounds of simulations using random methods, it generates different scenes due to probable variations of the input factors, for instance, labour cost, availability of resources, and changes in the scope of the project. This makes it easier for one to understand the risks that may be involved and the consequences that may accompany them Lambert (2018). Through the stochastic simulation, every uncertain variable is assigned probability distribution whereby the simulation generates a range of possible results within a practicing range to enhance the vision of project managers regarding the possible outcomes they may come across. In contrast to making a single-point estimate that would result in equal-periods or bar-chart risk, Monte Carlo simulation presents the probability distribution of costs or completion, the likelihood of under or over cost, or over or under time. This is useful for project managers to improve the decision making of risk management strategies, allocation of resources as well as contingency planning. Hence, the Monte Carlo simulation serves as a significant tool in risk assessment, optimization of decision making, and accuracy of the project estimate Linton and Solomon (2017). 2.3. Modeling Uncertainty with Monte Carlo Simulation The involvement of Monte Carlo simulation for handling with uncertainties means that project parameters are represented not as fixed values but as probability distributions. In conventional cost estimation, sources like materials cost, labour cost or time taken for the project is considered as a constant value, despite the fact that estimated may not remain constant. In contrast to these, Monte Carlo simulation is more consistent with the uncertainty that exists in each of these aspects because they characterize these factors in terms of distributions such as normal, triangular or uniform distributions from historical data or from data from experts. When the input variables have been declared as probability distributions, the Monte Carlo simulation executes numerous tests or the iterations to mimic a broad range of possibilities. For example, when the amount of material expenses cannot be well estimated, one number is not used, but instead, a range of possible values is provided, each of which is accompanied by the probability of the value occurring. By repeating this procedure numerous of times, it provides the simulation of prospective outcomes that give probability distribution. It subscribes to the concept of cost degredation and helps in postulating possibilities of cost contingent scenarios and the likelihood of different levels of risk Norsworthy and Szabo (2017). These results usually include basic measures of average, spread, and percentiles, and they provide a good understanding of the range of possible outcomes. These points are useful to the project leaders as they help in determining how much exposure to risks a project has then allocate risks according to the damage they can cause. For instance, when the simulation shows that a project is likely to go over the given budget in an amount described, it becomes the project managers’ chance to alter the budget or take preventive measures leading to potential high-cost aspects. This makes the use of Monte Carlo simulation as a way of analyzing uncertainty better and malleable approach in handling project risks afforded than from a deterministic point of view. Idea of such a strategy allows demonstrating capabilities of approaching results more clearly and minimizes inaccuracies concerning time-line and cost estimations O’Neill (2017). Monte Carlo simulation has numerous uses in the field of risk management which is particularly relevant in situations that involve a high level of risks within construction and engineering, finance and software development projects among others. The most evident role of Monte Carlo simulation in risk management is that it helps to quantify and analyze risks related to cost and time volatility. Monte Carlo approach is a wider view on potential risks and their economic impact based on the modelling of different possible variations of the unpredictable aspects of the project. In the context of risk management, Monte Carlo simulations offer an effective method in regards to the possible risks such as time delay, cost overruns, and shortages of resources. For instance, a project manager can analyze the impacts that may be caused by changes in material costs, changes in production rates in the project or even changes in the size of the project. This makes it easier for the project teams to have a better view as to the likelihood of such events and evaluate the potential consequences they may have on the project’s financial plan and schedule Peters and Smith (2016). Besides, it helps in identifying fundamental risk factors through executing simulations across number of scenarios. Focusing on the preliminary probabilistic factors that have the biggest impact associated with a particular project, teams are in the position to reallocating resources as a way of enabling the categorisation and minimisation of risks. Ashforth & Gibbs also realize the urgency of enhancing the production of better risk minimization approaches. For instance, if the simulation shows a high risk of budget oversights due to changes in materials’ prices, the project managers may choose to fix prices before the commencement of the project, search for other nurseries, or include a cushion fund. Perhaps one of the most vital applications of Monte Carlo simulation is in project portfolio management whereby the total risk for all the projects can be determined and impact of each project on the portfolio as a whole can be assessed easily. This helps in decision-making as to the allocation of resources and the prioritization of prospects as per the risk rating Rasmusen (2017). The Monte Carlo simulation improves the endeavor of cost estimation by providing a stochastic technique that allows the approximation of costs unlike the most basic strategies used in ventures that rely on cost estimates. Traditional methods of estimating such as expert judgments or analogous estimating commonly deal with point estimates which can be highly inaccurate especially when the project is faced by high levels of risk and uncertainty with respect to one or more parameters. However, the Monte Carlo simulation takes the ability of the input variables into account by presenting input variables probabilistic distribution instead of deterministic Sargent (2018). This results in a production of a range of cost possibilities and gives the project managers a better insight into more possible costs that might occur, the likelihood of going over the anticipated costs and the associated risks. In contrast to relying to one figure that could be incorrect, project managers can weigh through all the various types of the expenses and the probability of a situation occurring. This also makes them more prepared for the shocks, allocate the resources better and base their decisions about the funding of projects and the management of risks on accurate information. Besides that, the Monte Carlo simulation enhances the cost estimate by identifying the critical cost drivers and their impact on the total project financial cost plan. For instance, if the simulation reveals that variability of labour costs is relatively high and their influence on the cost is significant, the project managers can take necessary actions to minimize threats associated with the labour costs. In some cases, it may mean changing project schedules, pre-securing labour agreements or researching on other means of human resource acquisition Tavares and Batista (2016). Moreover, the Monte Carlo simulation presents a statistical outcome which includes average, standard deviation, and percentiles, which assist in giving a measure of risk attached to cost estimates. This empowers the project managers into developing better cost risk buffers and overall evaluating the probability of staying on the cost initially set. Monte Carlo simulation just enables more accurate cost prediction thus enables better management of costs reducing the risk on cost overruns and increasing the chances of a successful project completion Vose (2016). 2.4. Role of Random Sampling in Monte Carlo Analysis Random sampling is also important in Monte Carlo analysis which is the basis of generating numerous results for a certain problem depending on the variation in the input factors. Monte Carlo simulations are based on principles of randomness in order to analyze the behaviors of complex systems and also to measure risks various circumstances. In Monte Carlo analysis, the random sampling is a process of selecting random probability distributions for variables such as costs of the project, cost of labours, rates of materials and other variables. They use historical data, opinion from professionals or other assumptions, and they just show the range for the possible values of each variable. For example, when a project manager is in a state of indecision regarding the costs of attending a particular material costs, he/she can, therefore, take advantage of normal distribution where by the distribution is defined on the basis of the mean value and the standard deviation of cost fluctuation Zhang and Liu (2017). Once the probability distribution of each of the inputs has been defined, random samples are drawn from these distributions and the simula- tion is performed for each set of values of the inputs so obtained. This procedure is constrained by being often repeated, indeed sometimes thousands or even millions of times in order to mimic a great number of different circumstances. Each generation produces a completely different outcome based on different probability distribution of the input parameters. As a result of the Monte Carlo analysis by using the technique of random sampling, the total range of risk and benefit options can be identified comprehensively. The results of these simulations are then analyzed for significance and these usually comprise the likelihood of the Cost control-situations going over the budgeted amount and likelihood of controlling the time control situations for the project and the range of probable expenses or time lines of project completion. It assists decision makers in arriving at a better estimation of risks and resource allocation, and expenditure as well as time line for project completion Zio (2017).
3. RESEARCH METHODOLOGY The research methodology for this study focuses on the use of Monte Carlo simulations to evaluate the cost contingency and risk assessment within project management. The methodology includes the following steps: 3.1. Monte Carlo Simulation Setup 1) Identification of Project Cost Input Variables: The first activity in undertaking the simulation is to define the key decision variables that will increase or decrease the cost of the project including the cost of the materials to be used and cost of labour to be incurred as well as the length of time required to complete a project. All these factors are stochastic and are represented by probability distribution functions, namely, normal, triangular or uniform distribution. 2) Data Gathering: The information from previous similar projects, experienced professionals, and generally accepted practices in the industry are used to obtain the distribution of probability of the input variables. For instance, if the price fluctuations were normally distributed within a particular period, then such a cost type can be represented by the normal distribution equation based on the past price changes; if the distribution of the project reports indicates the triangular type distribution, then the cost of such type can be approximated by the triangular distribution. 3) Monte Carlo Simulation: There are several rounds of the Monte Carlo analysis performed with the specified activity, where thousands of cases can be modeled in order to generate numerous scenarios. For each iteration the values of the input random variables are simulated according to the probability distribution which has been assigned to them and the cost of the project is computed. The result of the simulation will be a chance of certain costs, which will enable determination of the probabilities of the results that may be expected. 4) Risk Evaluation: The scenarios generated from the simulation are evaluated in order to determine the extent of exposure to particular risks in the course of the project. For instance, likelihood of cost overruns or delays is estimated and the risk associated to the project is determined based on such probabilities. 5) Sensitivity Analysis: Sensitivity analysis is used to identify those variables that have most dictation on the total cost of the project. It is especially beneficial for paying equal attention to high risk variables and making correct decisions about where to spend contingency money or to implement correction actions. 3.2. Validation and Verification For the credibility of the outcomes generated by the Monte Carlo simulations, the model is checked and verified with historical project data and the judgment of experts. The above outcomes of the simulation are then compared to past similar projects in order to check the validity of the results. Moreover, the sensitivity analysis is employed in order to check the stability of the obtained results and determine that they have no significant relation to the specific assumptions and values used in the work. 4. DATA ANALYSIS The assessment of risks and the measurement of the performance of the cost forecasts derived from the Monte Carlo simulation is another reason for data analysis in this study. The next subheadings show the procedure of analysis and the results in that order as stated below next. Several analyses can be undertaken on the Monte Carlo simulations carried out and these are as explained below; 1) Cost Distribution Analysis: This has to do with the distribution of total project cost within several simulation runs. This way, after constructing the histograms of the outcomes, one is able to evaluate the distribution of the costs for ascertaining the probability of going over one’s set budget limit. 2) Probability of Exceeding Budget: One of them is being able to establish the possibility of a project’s cost exceeding the first estimate. This calculation is done at an occupancy cost level that looks into the number of simulation runs within which the total project cost is higher than the provided budget. 3) Cost Reallocation: This alignment focuses on the change in a project’s costs from one simulation run to another. The variation in the cost outcomes is determined and the extent of variability involved in the implementation of the project is ascertained. 4) Risk Sensitivity Analysis: This analysis helps in determination of the variables that significantly affect the total cost. By identifying the dependency of the cost on the input variables such as the cost of materials and man power, it becomes easy to establish region that many lead to increased costs like; cost of material, cost of labor among others. The next two tables present the summary of the Monte Carlo simulation as well as the analysis to identify cost uncertainty, risk, and variability. The identified method comprises the sensitivity analysis as a tool that determines the risky factors and the cost distribution table that reflects the chances to exceed the budget. This has helped with decision making and shows the manager the risk areas that needs to be addressed and in this case, areas where cost control must be focused on. Table 1
This table illustrates how the total project cost varies across different simulation runs and shows the likelihood of the project exceeding its budget. For example, at Simulation Run 1, the cost is $1,100,000 with a 10% chance of exceeding the budget, while at Simulation Run 10, the cost increases to $1,550,000 with a 100% chance of exceeding the budget. The table helps project managers understand the range of possible costs and assess the probability of going over budget. Table 2
This table identifies which factors have the most significant impact on project costs. Material costs have the largest influence (40%), meaning any change in material prices can greatly affect the overall cost. Labor costs follow at 30%, indicating that inefficiencies or delays in labor can also significantly increase costs. Project duration impacts costs by 20%, and resource availability is the least influential at 10%. This analysis helps focus attention on the most critical factors that affect the project’s budget. Table 3
This table highlights how project costs vary across different risk scenarios. In Scenario 1 (base), the average cost is $1,200,000 with a variability of 12.5%, indicating moderate cost stability. In Scenario 2 (high risk), the average cost increases to $1,400,000 with higher variability (17.86%), showing more uncertainty in costs. In Scenario 3 (low risk), the cost drops to $1,100,000 with the least variability (9.09%), suggesting a more predictable cost outcome. This table helps project managers understand the potential range of costs depending on risk levels. Table 4
This table evaluates the likelihood and financial impact of different risks on the project. For instance, high material costs have a 30% chance of increasing costs by $500,000, and labor shortages have a 25% chance of adding $300,000. Project delays, scope creep, and regulatory changes also present risks, with varying impacts and likelihoods. The table also suggests mitigation strategies like securing fixed-price contracts or improving scheduling. This risk assessment guides project managers in preparing for and addressing the most critical risks. 5. CONCLUSION It is befitting to say that the Monte Carlo simulation is a sound way of dealing with uncertainty that project managers encounter in the assessment of the cost and risks associate with a project. It allows for the probability of a variety of outcomes to be explored since this methodology of random sampling allows the usage of a large number of probable distributions, thus providing a more accurate picture as to the risks involved in a certain project. while conventional cost estimating produced individual point estimate, Monte Carlo simulation provides a variety of possible outcomes and probability associated with each, which make the decision making in uncertainty more effective and readiness for worst case scenario better. The use of Monte Carlo simulation in the field of financial forecasting increases the degree of accuracy on stated budgeted cost incorporating variability in uncertainty; this makes managers have a good look at the risks and possible over cost of projects. Conclusively, it creates better decision-making on the utilization of resources, risks’ probability, and project timelines that in turn have more prospects in successful completion of projects. As the initiatives become more complex and the factors that influence the accomplishment of initiatives increase in volatility, Monte Carlo simulation appears as a critical factor. Monte Carlo simulation improves risk management strategies together with the probabilistic method in risk evaluation and cost estimation and offers reliable and reliable project outcomes; therefore, it becomes indispensable for project managers across different industries.
CONFLICT OF INTERESTS None. ACKNOWLEDGMENTS None. REFERENCES Aven, T. (2016). Risk analysis: Assessing Uncertainties
Beyond Expected Values and Probabilities.
Wiley. Baillie, C. (2015). Monte Carlo Simulation in Project Management. Wiley
& Sons. Barlow, R. E., & Proschan, F. (2017). Mathematical Theory of Reliability.
SIAM. Beasley, M. S., & Tootell, R. L. (2018). Using Monte Carlo Simulation to Optimize Project Costs and Risks.
Journal of Project Management, 24(3), 175–185. Beck, R. J. (2019). Quantitative Methods for Project Management:
Forecasting, Decision-Making,
and Risk Analysis. McGraw-Hill Education. Belton, V., & Stewart, T. J. (2018). Multiple
Criteria Decision Analysis:
An Integrated Approach. Springer. Blanchard, B. S., & Fabrycky, W. J. (2017). Systems Engineering and analysis
(5th ed.). Pearson Education. Brown, M. D., & Hwang, C. L.
(2017). Monte Carlo Simulation in Risk Analysis and Project Management. Wiley. Burgess, M. M. (2017). Monte Carlo Techniques in Project Risk Management. International
Journal of Project Management, 34(5), 423–430. Cardoso, A., & Figueira, J. (2017). Project
Risk Management Using Monte Carlo Simulation. Journal
of Risk Analysis, 13(2), 122–134. Clarke, L., & Mattern, A. (2016). Risk Analysis in Project Management Using Monte Carlo Methods. Springer. Coyle, M. (2016). The Application of Monte Carlo Simulations in Cost Estimating. Journal of Cost Engineering, 30(4), 58–66. Der Kiureghian, A., & Ditlevsen, O. (2017). Aleatory and Epistemic Uncertainty in Probabilistic Risk Analysis. Springer. Drucker, P. F. (2017). The Practice of Management. Harper & Row. Glickman, S. D. (2016). Project Cost and Risk Analysis with Monte Carlo Simulation. Project Management Journal, 25(4), 31–41. Hillson, D., & Simon, P. (2017). Practical Project Risk Management: The ATOM Methodology(2nd ed.). Management Concepts. Hoffmann, M. (2018). Monte Carlo Simulations for Cost and Risk Assessment. Journal of Financial Risk Management, 11(2), 91–100. Kunsch, A. (2017). Stochastic Methods in Engineering: Monte Carlo Simulations in Risk Analysis. Springer. Laituri, M. (2017). Risk Management Techniques in Project Management Using Monte Carlo Simulation. Project Management Quarterly, 39(3), 22–30. Lambert, M. (2018). Risk Management for Project Managers: A Monte Carlo Approach. Wiley. Linton, C., & Solomon, A.
(2017). Monte Carlo Simulations and their Impact on Risk Management. Journal of Project
Management, 45(6), 249–259. Norsworthy, M., & Szabo, R. (2017). Monte Carlo methods in Financial Analysis. Cambridge University Press. O’Neill, R. (2017). Application of Monte Carlo Simulations in Project Scheduling. International Journal of Project Risk Management, 16(3), 22–37. Peters, R., & Smith, P. (2016). Understanding Monte Carlo Simulations in Cost Analysis. Financial Engineering Journal, 14(4), 134–144. Rasmusen, E. (2017). Monte Carlo Methods for Engineering and Financial Applications. Wiley & Sons. Sargent, R. G. (2018). Verification and Validation of Simulation Models in Monte Carlo Analysis.
Journal of Simulation, 15(3), 204–210. Tavares, S. F., & Batista,
A. (2016). Project Risk Management:
Methods and Monte Carlo techniques. Routledge. Vose, D. (2016). Risk Analysis: A Quantitative
Guide (3rd ed.). Wiley. Zhang, L., & Liu, X. (2017). Monte Carlo Simulations in Business and Engineering Risk Management.
Springer. Zio, E. (2017). The Monte Carlo Method in Risk Analysis and Decision-Making. Wiley.